近年来,随着我国轨道交通线路的发展,盾构法施工技术在开挖地铁隧道时得到了越来越多的广泛采用。埋设有地下高压燃气管线的地段,不可避免地会受到地铁盾构施工的影响,因此对盾构隧道下穿对地下高压燃气管线沉降影响的研究是十分迫切的。基于此,本文以杭州某地铁盾构施工区间开挖隧道及其上方的杭甬线燃气管线为工程对象,通过Abaqus有限元软件对盾构掘进参数对地下高压燃气管线的沉降影响进行了分析,发现在不同工况和不同开挖参数下,地下管道的地层沉降和变形是不同的。结果表明,管道的最大沉降量位于隧道中心线的上方,并且沉降量会随着水平距离的增加而减小;盾构管线与隧道交叉角度小时,引起的管线沉降变形将会小一些;确定了盾构掘进参数的安全取值范围。 In recent years, with the development of our country’s rail transit lines, shield construction technology has been more and more widely used in the excavation of subway tunnels. Sections with underground high-pressure gas pipelines will inevitably be affected by the construction of subway shields. Therefore, it is very urgent to study the impact of shield tunnels on the settlement of underground high-pressure gas pipelines. Based on this, this article takes the excavation of a tunnel in a shield construction section of a subway in Hangzhou and the gas pipeline on the Hangyong line as the engineering object, and analyzes the influence of shield tunneling parameters on the settlement of the underground high-pressure gas pipeline through Abaqus finite element software. It is found that under different working conditions and different excavation parameters, the ground settlement and deformation of underground pipelines are different. The results show that the maximum settlement of the pipeline is above the centerline of the tunnel, and the settlement will decrease with the increase of the horizontal distance; when the crossing angle between the shield pipeline and the tunnel is small, the pipeline settlement deformation caused by it will be smaller; the safe value range of the shield construction tunneling parameters is determined.
近年来,随着我国轨道交通线路的发展,盾构法施工技术在开挖地铁隧道时得到了越来越多的广泛采用。埋设有地下高压燃气管线的地段,不可避免地会受到地铁盾构施工的影响,因此对盾构隧道下穿对地下高压燃气管线沉降影响的研究是十分迫切的。基于此,本文以杭州某地铁盾构施工区间开挖隧道及其上方的杭甬线燃气管线为工程对象,通过Abaqus有限元软件对盾构掘进参数对地下高压燃气管线的沉降影响进行了分析,发现在不同工况和不同开挖参数下,地下管道的地层沉降和变形是不同的。结果表明,管道的最大沉降量位于隧道中心线的上方,并且沉降量会随着水平距离的增加而减小;盾构管线与隧道交叉角度小时,引起的管线沉降变形将会小一些;确定了盾构掘进参数的安全取值范围。
高压燃气管线,有限元,沉降量,掘进参数
Shucai Wang
China Railway 19th Bureau Group Rail Transit Engineering Co., LTD., Beijing
Received: Aug. 26th, 2021; accepted: Sep. 21st, 2021; published: Sep. 28th, 2021
In recent years, with the development of our country’s rail transit lines, shield construction technology has been more and more widely used in the excavation of subway tunnels. Sections with underground high-pressure gas pipelines will inevitably be affected by the construction of subway shields. Therefore, it is very urgent to study the impact of shield tunnels on the settlement of underground high-pressure gas pipelines. Based on this, this article takes the excavation of a tunnel in a shield construction section of a subway in Hangzhou and the gas pipeline on the Hangyong line as the engineering object, and analyzes the influence of shield tunneling parameters on the settlement of the underground high-pressure gas pipeline through Abaqus finite element software. It is found that under different working conditions and different excavation parameters, the ground settlement and deformation of underground pipelines are different. The results show that the maximum settlement of the pipeline is above the centerline of the tunnel, and the settlement will decrease with the increase of the horizontal distance; when the crossing angle between the shield pipeline and the tunnel is small, the pipeline settlement deformation caused by it will be smaller; the safe value range of the shield construction tunneling parameters is determined.
Keywords:High-Pressure Gas Pipeline, Finite Element, Settlement, Tunneling Parameters
Copyright © 2021 by author(s) and beplay安卓登录
This work is licensed under the Creative Commons Attribution International License (CC BY 4.0).
http://creativecommons.org/licenses/by/4.0/
为了缓解我国地上城镇的交通压力,人们把目光转向地下空间。盾构法因为其在施工过程中干扰小、技术比较成熟、安全可靠等优点,得到了越来越广泛的应用 [
杭州地铁8号线青六路站~青蓬路站区间盾构转换井区间隧道采用盾构法进行施工,盾构隧道的外径6.44 m,区间左线起止里程右DK5 + 801.633~右DK5 + 918.525,右线长116.892 m。右线起止里程右DK5 + 801.633~右DK5 + 918.525,右线长116.892 m。线路纵断面呈“一”字坡,区间最小坡度2‰,最大坡度4‰,区间最大埋深10.8 m,最小埋深9.7 m。线路沿线分布建(构)筑物主要有三联横河、省天然气杭甬线管道等。盾构区间下穿高压燃气管线,其管径Φ813 mm,壁厚11.9 mm,6.3 Mpa,盾构隧道的设计采用的是左右线分修的两条单线隧道。
根据勘察的资料,盾构隧道下穿下高压燃气管线地质情况如表1所示,本施工项目在隧道开挖处的土层信息中粉土、砂质土占据着主要成分,因此本文以粉砂土层作为研究对象。
材料 | 密度(kg/m3) | 泊松比 | 粘聚力c (kPa) | 内摩擦角φ (˚) | 渗透系数(m/s) |
---|---|---|---|---|---|
杂填土 | 1910 | 0.3 | 10.0 | 12.0 | 1.1 × 10−7 |
粉质粘土 | 1980 | 0.3 | 30.0 | 20.0 | 1.1 × 10−7 |
粉土 | 1980 | 0.3 | 10.0 | 25.0 | 1.1 × 10−7 |
粉质粘土 | 1980 | 0.3 | 30.0 | 20.0 | 1.1 × 10−7 |
粉土 | 1980 | 0.3 | 10.0 | 25.0 | 1.1 × 10−7 |
粉砂 | 1890 | 0.27 | 5.0 | 33.0 | 1.1 × 10−6 |
粉质粘土 | 1980 | 0.3 | 30.0 | 20.0 | 1.1 × 10−7 |
粉砂 | 1970 | 0.25 | 5.0 | 30.0 | 1.1 × 10−6 |
表1. 各地质层土质参数信息
高压燃气管线是我们国家的重要管道,经与相关部门沟通和计算,高压燃气管线保护控制技术要求为 [
根据盾构区间与高压燃气管线的相对位置关系,利用有限元软件建立仿真模型,取高压燃气管线与开挖隧道成30˚、60˚、90˚三种不同角度的工况,如图1所示。
为了使计算结果更加准确,减少边界条件的影响,在进行建模时,模型的范围是100 m × 50 m × 60 m,高压燃气管线外径813 mm,壁厚11.9 mm,埋深1.2 m,高压燃气管线中心线与盾构隧道中心线垂直距离为6.9 m。模型的边界条件为:在模型四周边界施加法向约束,模型底部施加全约束,模型上表面为自由面。土体的计算参数如表1所示。
隧道开挖模拟主要分为以下几步:计算盾构开挖前土体的初始应力,得到土体的初始应力应变状态;利用ABAQUS生死单元杀死一个衬砌管片宽度的待开挖土体单元,由盾构壳体支承隧洞一周的未开挖土体,在盾构机尾部处进行衬砌管片的铺设;盾构开挖推进到下一步长,利用ABAQUS生死单元激活衬砌单元,利用衬砌管片的支承来替代开挖处土体,施加注浆产生的均布压力于盾尾;重复以上第2、3步的过程,直至盾构开挖通过高压燃气管线一定距离。
高压燃气管线与开挖隧道所成角度分别为30˚、60˚、90˚时不同土压力对高压燃气管线的沉降影响模拟结果如图2所示。
图1. 仿真模型
从图2中我们可以看出,在土压力大小在1.0 bar时管线的沉降变形最大,且在高压燃气管线与开挖隧道所成角度为90˚时管线的沉降变形超过了管线安全变形值20 mm,在1.25 bar时管线的沉降变形次之,在1.5 bar时管线的沉降变形最小。
高压燃气管线与开挖隧道所成角度分别为30˚、60˚、90˚时不同推进力对高压燃气管线的沉降影响模拟结果如图3所示。
从图3中我们可以看出,推进力大小在10,000 kN时管线的沉降变形最大,在125,000 kN时管线的沉降变形次之,在15,000 kN时管线的沉降变形最小。在管线与开挖隧道成90˚时管线的沉降变形最大,在60˚时次之,30˚时变形最小。
图2. 不同土压力下盾构开挖对地下管线沉降的影响
图3. 不同推进力下盾构开挖对地下管线沉降的影响
高压燃气管线与开挖隧道所成角度分别为30˚、60˚、90˚时不同刀盘扭矩对高压燃气管线的沉降影响模拟结果如图4所示。
图4. 不同刀盘扭矩下盾构开挖对地下管线沉降的影响
从图4中我们可以看出,盾构刀盘扭矩大小在2200 kN∙m时管线的沉降变形最大,在1700 kN∙m时管线的沉降变形次之,在1200 kN∙m时管线的沉降变形最小。且在90˚下管线的沉降变形超过了安全变形值20 mm,在60˚下变形次之,在30˚下变形最小。
高压燃气管线与开挖隧道所成角度分别为30˚、60˚、90˚时不同刀盘转速对高压燃气管线的沉降影响模拟结果如图5所示。
图5. 不同刀盘转速下盾构开挖对地下管线沉降的影响
从图5中我们可以看出,盾构刀盘转速 [
本文根据杭州地铁8号线桥头堡站~盾构转换井区间下穿地下高压燃气管线,通过有限元仿真,分析了不同盾构掘进参数对管道沉降量的影响,主要结论如下:1) 管道的最大沉降量位于隧道中心线的上方,并且沉降量会随着水平距离的增加而减小。2) 盾构管线与隧道交叉角度尽可能小一些,且尽量避开90˚。3) 盾构掘进参数的安全取值范围为土压力1.25 bar左右、推进力12,500 KN左右、刀盘扭矩1700 KN∙m左右、刀盘转速1.2 rpm左右。
王树才. 杭州某盾构隧道下穿对其地下高压燃气管线沉降影响研究The Influence of the Underpass of a Shield Tunnel on the Settlement of Underground High-Pressure Gas Pipelines in Hangzhou[J]. 土木工程, 2021, 10(09): 894-900. https://doi.org/10.12677/HJCE.2021.109101